WCRC: Paving & Pathway Work Continues on Textile Road between Campbell Road and Platt Road

WCRC Logo
The WCRC is planning to pave the first layer of asphalt on Textile Road between Campbell Road and Platt Road in mid-June, if the weather cooperates.

This first layer will cap the gravel and grading work that has already been completed, protecting the roadbed from weather and construction traffic. Once this first layer has been installed, the WCRC will focus on building the pathway. The WCRC plans to substantially complete the pathway before paving the final two layers of asphalt on the road later this summer.

The WCRC still expects the project to be completed by the end of July. As a reminder, Textile Road remains closed to ALL traffic from the Thomas Road intersection to just west of Platt Road in Pittsfield Township.

If you have any questions concerning this work, please contact Mark McCulloch of the WCRC at 734.327.6679, or via email at mccullochm@wcroads.org.