Posted on: August 11, 2023
Work continues for the project on Platt from US-12 to Wall Park:
Erie Construction is still about one week behind schedule.. Erie has paved most of the pathway and expects to complete the remaining paving this week. The contractor will now start...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: July 25, 2023
Work continues for the project on Platt from US-12 to Wall Park:
Erie Construction is about one week behind schedule but still believe that they will be able to complete on time. Erie is currently completing yard drain installation and placing fi...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: July 10, 2023
Work continues for the project on Platt from US-12 to Wall Park.
- Over the past two months of storm sewer installation along the west side of Platt, the contractor has finally begun to install the new curb in locations along the pathway. As part o...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: May 3, 2023
Work continues for the project on Platt from US-12 to Wall Park.
- The contractor has completed the mainline storm sewer and has graded the projected pathway. Currently, the contractor is stripping topsoil in preparation for placing the aggregate base for th...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: April 10, 2023
PRG II Project Update:
Work is on schedule and continues on the project on Platt from US-12 to Wall Park
- Existing sidewalk has been removed from the future pathway locations
- Storm sewer is being installed to ensure proper drainage for the project a...
Read on...
Additional Info...
Platt Road Greenway II Project
Posted on: March 16, 2023
On February 23, 2023, the Washtenaw County Road Commission held the Preconstruction Meeting for the project. The schedule start date for this project is 3/1/2023, and the scheduled completion date is 9/29/2023. Erie Construction plan...
Read on...
Additional Info...
Platt Road Greenway II Project